138kvMonopole
If you’ve recently been contacted by Brazos Electric Power Cooperative (“Brazos”) regarding the construction of a transmission line, it is important that you act now! Landowners MUST intervene in order to have a say in the final route. There are multiple opportunities to influence the process, but to have the greatest impact you must start the process early and with an experienced team of professionals. Please contact us today to schedule a free, 30-minute consultation to learn more about how Braun & Gresham, PLLC can help protect your land.
 

 

 

 

 

Transmission Lines in the Routing Phase:

Cogdell to Clairemont

  • PUC Docket # 47808
  • Joint project with Oncor Electric
  • Kent and Scurry counties
  • 138kv monopole
  • 70 ft. right of way
  • 85 ft. tall
  • Intervention deadline: January 22, 2018
  • Waiting for final order

Gyp to Benjamin

  • PUC Docket # 47691
  • Joint project with AEP
  • King and Knox counties
  • 138kv monopole, single circuit, single pole steel construction
  • 100 ft. right of way
  • 80-100 ft. tall
  • Intervention deadline: December 29, 2017
  • Waiting for final order

Transmission Lines in the Condemnation Phase:

Kittyhawk

  • PUC Docket # 46429
  • Collin county
  • 138kv, single pole, circuit bundled line
  • 70-100 ft. right of way
  • 120 ft. tall
  • Intervention deadline: 11/28/16
  • Constraints Map

Previous Lines:

Oak Point # 45170 – final order 7/28/16

Stonebrook # 44060 – final order 6/13/16

Parvin # 43878 – final order 3/30/16