Overview

The Public Utility Commission of Texas released the “Fred” Transmission Line project (PUC Docket No. 50485) by Sam Houston Electric Cooperative, Inc.

Project Details:

  • Affected Texas County: Tyler
  • Power Line Voltage: 138-kV Line
  • Easements Requirements: 100 ft Easement Required
  • Power Line Height: 85-115 ft
  • Final Order Issued: July 8, 2021

Project Updates:

Braun & Gresham is working with local landowners, and recently learned that Sam Houston Electric Cooperative, Inc. is surveying properties and acquiring the land needed to construct the transmission line.

Are you an impacted landowner?

Time is of the essence when your property is going be taken in condemnation. Do not wait until it is too late to learn about your rights.

To receive a complimentary map of your property and the proposed taking, and schedule a 30-minute consultation with one of our condemnation attorneys, please complete the form below or call (512) 690-4388.


[caldera_form id=”CF615e006e89ec8″]

The Braun & Gresham Condemnation Team

Patrick L. Reznik
Attorney & Counselor
Carly Barton
Attorney & Counselor
Audrey Banner
Paralegal

At Braun & Gresham, our attorneys can help you before, during, and after the taking of your land. We will advise you on the best course of action and not only help you get full market value, but also help you protect the aspects you love most.

For more information about the project, or to learn about your rights in the condemnation process, please contact us at [email protected] or (512) 690-4388.